Story

The project began in May 2023 with the construction of structural shafts. Through Michigan’s changing seasons, the team installed brick, glass block, and precast. As with any project, this had its challenges, but through a wonderful partnership with First Companies, they were able to accomplish something they are very proud of.

Facts

Submitter: Kortman Masonry

Architect: Dixon Architecture

Size: 20,182 SF

Location: Ada, MI

Date contract completed: June 2025

Final contract value: $889,000

Project manager’s name: Nick Kortman

Superintendent’s name(s): Aaron Reichert, Ken Kortman

What percentage of the work scope was self-performed by your company? 100%