The Ottawa County Family Justice Center is a 57,000 SF three-story office building consisting of general office space, security holding cells, & six court/hearing rooms.
Submitter: Allied Mechanical Services
Architect: DLZ
Size: 57,000 SF
Title: Ottawa County Family Justice Center
Location: West Olive, MI
Date contract completed: April 2024
Final contract value: $4,486,000
Project manager’s name: Bill Smeda
Superintendent’s name(s): Theron Story
What percentage of the work scope was self-performed by your company? : 87%
eicawardsdev
on
July 1, 2024
Van Dyken Mechanical provided the engineering and installation of all duct work & gas piping for West Michigan Beef Company’s new facility. Exhaust fans, air curtains, louvers, unit heaters, split systems, & rooftop units were installed, with a VAV system with boiler reheat for office areas with zone control.
Submitter: Van Dyken Mechanical, Inc.
Size: 70,000 SF
Title: West Michigan Beef Company – Processing Facility
Location: Hudsonville, MI
Date contract completed: December 2023
Final contract value: $3,286,000
Project manager’s name: Jay VanDenBerg
Superintendent’s name(s): Tom Rybiski
What percentage of the work scope was self-performed by your company? : 100%
eicawardsdev
on
July 1, 2024
This 112,000 SF building appears as a one-story structure from the front but is actually two stories. Built on previously submerged land, it faced initial poor site conditions. A four-month delay in structural steel delivery didn’t alter the project schedule, demonstrating excellent teamwork. The building, designed for 5th and 6th graders, features numerous angles and no straight walls, posing additional challenges. Despite the tight schedule, NWK upheld high workmanship standards with a relatively young crew. Notably, the installation of two fire dampers per chase in confined spaces was particularly time-consuming. Additionally, the school includes a large snowmelt system.
Submitter: Northwest Kent Mechanical Company
Architect: GMB Architecture + Engineering
Size: 112,000 SF
Title: Hudsonville Public Schools – 5/6 Building
Location: Hudsonville, MI
Date contract completed: August 2023
Final contract value: $3,571,000
Project manager’s name: Derek Larson
Superintendent’s name(s): Tim Hanna
What percentage of the work scope was self-performed by your company? : 94%
eicawardsdev
on
July 1, 2024
This project was a complete renovation of the Boys & Girls Club of Muskegon. It ended up being two renovations in one due to fires set as the project was finishing. This caused the project to be completely redone. From devastating loss to triumphant salvation, the difficulties demonstrated resilience.
Submitter: Pleune Service Company
Architect: Concept Design Studio
Title: Boys & Girls Club of Muskegon Lakeshore
Location: Muskegon, MI
Date contract completed: April 2024
Final contract value: $2,216,000
Project manager’s name: Chad Martindale
Superintendent’s name(s): JC Piela
What percentage of the work scope was self-performed by your company? : 75%
eicawardsdev
on
July 1, 2024
Dunbar Hall is one of the most heavily used classroom buildings on campus. It houses the University’s College of Arts and Sciences, & features a cutting-edge podcasting, journalism, and broadcasting suite, active learning classrooms, & a state-of-the-art dance studio.
Submitter: DHE Plumbing and Mechanical
Architect: TowerPinkster
Size: 88,000 SF
Title: Western Michigan University – Dunbar Hall
Location: Kalamazoo, MI
Date contract completed: March 2024
Final contract value: $6,635,000
Project manager’s name: Jim Aho
Superintendent’s name(s): Dustin Healey, Austin Carris
What percentage of the work scope was self-performed by your company? : 70%
eicawardsdev
on
July 1, 2024
Triangle Constructors performed all general trades on Cascade Township’s new 18,000 SF fire station, which features four pull-through apparatus bays, living quarters, a fitness room, administration offices, a 48 FT high hose tower, & a high-rise training center.
Submitter: Triangle Constructors
Architect: Williams Architects
Size: 18,000 SF
Title: Cascade Township Fire Station No. 1
Location: Grand Rapids, MI
Date contract completed: November 2023
Final contract value: $970,000
Project manager’s name: Steve Johnson
Superintendent’s name(s): Mike Deters
What percentage of the work scope was self-performed by your company?: 100%
eicawardsdev
on
July 1, 2024
Kent County Road Commission’s Central Complex features a 18,000 SF storage building, a salt barn capable of housing 6,000 tons of salt, a fueling station, a loading dock and storage, a car wash, and a 36,000 SF administrative office building.
Submitter: Triangle Constructors
Architect: Hobbs+Black Architects
Size: 232,000 SF
Title: Kent County Road Commission – Central Complex
Location: Walker, MI
Date contract completed: November 2023
Final contract value: $674,000
Project manager’s name: Steve Johnson
Superintendent’s name(s): Mike Deters
What percentage of the work scope was self-performed by your company? : 100%
eicawardsdev
on
July 1, 2024
The Ferris State University – Center for Virtual Learning includes modern amenities like an EMI/RFI (electromagnetic interference/radio frequency interference) Shielding Room which reduces interference from external signals and devices, Information Security & Intelligence, and Digital Animation & Game Design. It also features the first built Esports Arena at a Michigan University. It is an amazing facility that revolutionizes the education experience!
Submitter: Nugent Builders
Architect: TowerPinkster
Size: 64,000 SF
Title: Ferris State University – Center for Virtual Learning
Location: Big Rapids, MI
Date contract completed: July 2023
Final contract value: $1,424,000
Project manager’s name: Ben Nugent
Superintendent’s name(s): Bob Lackey
What percentage of the work scope was self-performed by your company? : 50%
eicawardsdev
on
July 1, 2024
Olives restaurant underwent a six-week renovation, transforming both floors. The update included refreshed dining areas and restrooms, with the first floor also receiving a revamped bar area. Pioneer Millwork provided expert millwork and finishes, while Jean Stoffer of “The Established Home” on the Magnolia Network led the sophisticated design.
Submitter: Pioneer Construction
Architect: Jean Stoffer Design
Size: 1,200 SF
Title: Olives
Location: Grand Rapids, MI
Date contract completed: September 2023
Final contract value: $460,000
Project manager’s name: Dan Zaagman
Superintendent’s name(s): Wes Dickerson
eicawardsdev
on
July 1, 2024
This project consisted of an interior suite renovation and exterior storefront update to become Hughes Management’s new main office, featuring all new office, meeting, & work collaboration space.
Submitter: Pioneer Construction
Architect: AMDG Architects
Size: 10,000 SF
Title: Hughes Management
Location: Grand Rapids, MI
Date contract completed: January 2024
Final contract value: $3,600,000
Project manager’s name: Michael Verbeek
Superintendent’s name(s): Micah Frens, Phil Geurink
What percentage of the work scope was self-performed by your company? : 17%