U-Haul is a three-story storage facility designed with extensive reinforced concrete from the below-grade footings and walls up to the suspended level one slab to maintain the building’s structural integrity. This was a larger-scale concrete structure requiring knowledge, experience, large equipment, and a lot of manpower.
Facts
Submitter: Burgess Concrete Construction
Architect: Comprehensive Engineering
Size: 20,000 SF
Location: Walker, MI
Date contract completed: October 2024
Final contract value: $1,323,000
Project manager’s name: Joe Hunderman
Superintendent’s name(s): Tony Dykhouse & John Rogers
What percentage of the work scope was self-performed by your company? 99.7%
Hudsonville High School and Freshman Campus is a project that involved tall cast in place concrete walls, foundation, flatwork, sitework and polished concrete. The jobsite was tight and the schedule was precise. There was not one side of the school that was left without new concrete placed inside and out.
Facts
Submitter: Burgess Concrete Construction
Architect: GMB Architecture + Engineering
Size: 148,940 SF
Location: Hudsonville, MI
Date contract completed: October 2024
Final contract value: $3,737,000
Project manager’s name: Matt Burgess & Al Jeurink
Superintendent’s name(s): Matt Burgess & Jordan Burgess
What percentage of the work scope was self-performed by your company? 97.3%
The Western Michigan University Dunbar Hall renovation modernized and enhanced the building’s functionality with unique, high-quality materials. This comprehensive project significantly improved the space’s aesthetic and acoustic performance, creating a more engaging and efficient environment.
Facts
Submitter: Ritsema Associates
Architect: TowerPinkster
Size: 78,000 SF
Location: Kalamazoo, MI
Date contract completed: January 2024
Final contract value: $2,843,000
Project manager’s name: Trent Aukerman
Superintendent’s name(s): Norm Overhiser
What percentage of the work scope was self-performed by your company? 40%
The Ada Hotel is an amazing addition to the community. This project includes two restaurants and several hotel rooms. Each space displays unique high-end and technical features. It truly is one of a kind.
Facts
Submitter: Halyard
Architect: Dixon Architecture, OTJ Architects
Size: 38,445 SF
Location: Ada, MI
Date contract completed: November 2024
Final contract value: $2,800,000
Project manager’s name: Tom Maurer
Superintendent’s name(s): Brian McGhee
What percentage of the work scope was self-performed by your company? 90%
DeVries Jewelers is a local business that was looking to update their facility in the historic district of Grand Rapids. Kleyn Electric was instrumental in designing and building a new ground up facility that integrated updated security and technology while maintaining the historic charm of downtown Grand Rapids.
Facts
Submitter: Kleyn Electric Inc.
Size: 6,270 SF
Location: Grand Rapids
Date contract completed: December 2024
Final contract value: $231,000
Project manager’s name: Ryan Kooinga
Superintendent’s name(s): Kevin Kuiper
What percentage of the work scope was self-performed by your company? 96%
This project’s scope included concrete removal, foundation excavation, sand backfill, drain tile installation, concrete floor prep, and parking lot grading. Despite the challenges, working with other contractors on WMCI was enjoyable, and the finished product provided a high-quality result for the school.
Facts
Submitter: Dan’s Excavating Service, Inc.
Location: Grand Rapids
Date contract completed: August 2024
Final contract value: $52,000
Project manager’s name: Gideon Vanderwall
Superintendent’s name(s): Spencer Tellkamp
What percentage of the work scope was self-performed by your company? 100%
Topland Construction completed the successful installation of three modular block retaining walls for the 2024 City of Allendale Water Treatment Plant improvements.
Facts
Submitter: Topland Construction LLC
Size: 4,750 SF
Location: Allendale
Date contract completed: September 2024
Final contract value: $350,000
Project manager’s name: Nate Smith
Superintendent’s name(s): Caleb Glashower
What percentage of the work scope was self-performed by your company? 100%
HighPoint completed a ground-up build for Pro Star Aviation, providing full electrical design, access control, security, utility relocation, and a new taxiway with lighting and signage—all within an active airport. The project demanded precise coordination, safety compliance, and seamless integration with ongoing airport operations.
Facts
Submitter: HighPoint
Architect: Bowers+Associates
Location: Grand Rapids
Date contract completed: December 2024
Final contract value: $999,600
Project manager’s name: Joe Hailk
Superintendent’s name(s): Tyler Aungst
What percentage of the work scope was self-performed by your company? 100%
The Cadillac Public High School Renovation & Addition enhanced facilities for students, athletes, and staff. Ritsema met all deadlines, often ahead of schedule, with custom designs in the weight room, staircase, classrooms, cafeteria, kitchen, locker rooms, auditorium, and wellness center, showcasing high-quality workmanship and professionalism.
Facts
Submitter: Ritsema Associates
Architect: Tower Pinkster
Size: 155,000 SF
Location: Cadillac, MI
Date contract completed: August 2024
Final contract value: $1,219,000
Project manager’s name: Robert Brent, Sarah Connell
Superintendent’s name(s): Robert Brent
What percentage of the work scope was self-performed by your company? 75%
Paw Paw Early childhood center will be a great addition to the Paw Paw schools, allowing young children to learn motor skills with the track in the gym floor. Along with enjoying all the colors and patterns incorporating into the design of the building.
Facts
Submitter: Sobie Company
Architect: Tower Pinkster
Location: Paw Paw, MI
Date contract completed: February 2025
Final contract value: $262,000
Project manager’s name: Michael Brooks
Superintendent’s name(s): Jerrud Postma
What percentage of the work scope was self-performed by your company? 80%