The new public safety building integrates a fire and police station, separated by a truck bay. Designed for growth, it features LEED Silver certification, a multipurpose / training room, and ample truck access. Firefighter living quarters include private amenities like a kitchen, weight room, and lounge, along with shared facilities.
Facts
Submitter: Owen-Ames-Kimball Co.
Architect: DLZ
Size: 18,000 SF
Title: City of Kalamazoo Department of Public Safety Station 2
Location: Kalamazoo, MI
Date contract completed: October 2023
Final contract value: $9,460,000
Project manager’s name: Bob Byrne
Superintendent’s name(s): James Priest
What percentage of the work scope was self-performed by your company?: 0%
Tender Lawn Care has big plans for future growth in the greater Grands Rapids area. To help accommodate this growth, they hired Veneklasen Construction to build them a brand new, pre-engineered metal building (PEMB) to serve as an office and equipment storage facility.
Facts
Submitter: Veneklasen Construction
Architect: Ghafari Associates
Size: 33,000 SF
Title: Tender Lawn Care
Location: Kentwood, MI
Date contract completed: October 2023
Final contract value: $5,609,000
Project manager’s name: Nate LaDuke
Superintendent’s name(s): Jeffrey Kenney
What percentage of the work scope was self-performed by your company?: 21%
Tommy’s has a history of providing a wide range of services to boaters and water sports enthusiasts at several locations throughout Michigan, Colorado and Florida. In a recent move to continue growing their brand and upgrade their space and services, Tommy’s decided to build a new location in Clermont, Florida.
Facts
Submitter: Orion Construction
Architect: Henrickson Architecture
Size: 15,000 SF
Title: Tommy’s Boats
Location: Comstock Park, MI
Date contract completed: March 2023
Final contract value:$5,000,000
Project manager’s name: Jeff Smigielski
Superintendent’s name(s): Jacobus Maas
What percentage of the work scope was self-performed by your company?: 0%
The office space, 12,000 SF, will house private offices, multiple conference rooms, a training room, bathrooms, gathering/break space(s), and much more. Additionally, there will be 15,000 SF of warehouse space that will be utilized to support the growing demands for our construction and development operations.
Facts
Submitter: CarbonSix Construction
Architect: Progressive Companies
Size: 28,000 SF
Title: Vision Real Estate & CarbonSix – Headquarters
Location: Grand Rapids, MI
Date contract completed: July 2023
Final contract value: $5,000,000
Project manager’s name: Mark Stauffer
Superintendent’s name(s): Ian Martin
What percentage of the work scope was self-performed by your company?: 15%
Triangle led the successful completion of Cascade Township’s new fire station, which features four pull-through apparatus bays, 48 FT high hose tower and high-rise training area, decontamination areas, emergency operations center, conference rooms and more.
Facts
Submitter: Triangle Associates
Architect: Williams Architects
Size: 18,000 SF
Title: Cascade Township Fire Station No. 1
Location: Grand Rapids, MI
Date contract completed: October 2023
Final contract value: $9,800,000
Project manager’s name: Nick Ballou
Superintendent’s name(s): Kyle May
What percentage of the work scope was self-performed by your company?: 15%
Buist was the Design Assist partner for construction of the new Otter Air Service facility, an air carrier in Grand Rapids, MI providing concierge private air transportation. Buist installed all low voltage IT network infrastructure, audio visual, and physical security, incorporating many elements into a single system for the end-user.
Facts
Submitter: Buist Electric
Architect: Integrated Architecture
Size: 40,000 SF
Title: Otter Air Services – Hangar & Corporate Office
Location: Grand Rapids, Michigan
Date contract completed: April 2024
Final contract value: $221,000
Project manager’s name: Jason Williams
Superintendent’s name(s): Jared Doot
What percentage of the work scope was self-performed by your company? : 100%
BCPS, Robert Nickels Intermediate School has special Music, Media and STEM Classrooms. From Cameras to view, Clocks that informed, AV systems that ROCKED, and Cabling that delivered high streaming systems. Town and Country’s attention to the details ensures all these systems are operating effectively well into the future!
Facts
Submitter: Town & Country Group
Architect: TowerPinkster
Size: 134,000 SF
Title: Byron Center Public Schools – Nickels Intermediate School
Location: Byron Center, MI
Date contract completed: August 2023
Final contract value: $1,093,000
Project manager’s name: Chad Guy
Superintendent’s name(s): Ben Doorn
What percentage of the work scope was self-performed by your company? : 100%
Confronted with increasing bandwidth requirements, Western Michigan University needed to upgrade their wireless infrastructure. As their low voltage partner, Feyen Zylstra provided expertise in the campus-wide wireless upgrade. Covering five campus buildings, FZ approached each as a separate project, considering occupancy needs, layouts, infrastructures, and challenges in our approach.
Facts
Submitter: Feyen Zylstra
Architect: Western Michigan University
Size: 695,000 SF
Title: Western Michigan University
Location: Kalamazoo, MI
Date contract completed: February 2024
Final contract value $353,000
Project manager’s name: Nick Gosdzinski
Superintendent’s name(s): David Smith, Nick Martinez
What percentage of the work scope was self-performed by your company? : 100%
Cardinal Vulcan is a four unit assisted living facility with two buildings designed for enhanced memory care services. GVA installed easy to use access controls, surveillance, intercoms, networking, and nurse call systems. All systems needed little to no reoccurring fee and could all simultaneously be viewed/access from a mobile device.
Facts
Submitter: Grand Valley Automation, Inc.
Size: 25,000 SF
Title: Care Cardinal Norton Shores – Assisted Living Facility
Location: Norton Shores, MI
Date contract completed: December 2023
Final contract value: $197,000
Project manager’s name: Cory Tate
Superintendent’s name(s): Matt Peters
What percentage of the work scope was self-performed by your company? : 100%
Grand Valley Automation completed a HVAC control system renovation for Interurban Transit Partnership, The Rapid. The HVAC controls include low voltage wiring, a vast array of sensors to properly control the HVAC equipment in the building. Part of the renovation included retrofitting from gas fired heat to hot water heat.
Facts
Submitter: Grand Valley Automation, Inc.
Architect: Progressive Companies
Title: The Rapid – Administrative Headquarters
Location: Grand Rapids, MI
Date contract completed: December 2023
Final contract value: $200,000
Project manager’s name: Coy Rottier
Superintendent’s name(s): Coy Rottier
What percentage of the work scope was self-performed by your company? : 100%