This 14,000 SF distillery, nestled in the forest alongside the White Pine Trail in Rockford, is part tasting room, restaurant, nature observatory and part production, warehouse, and distribution facility. Wolverine Building Group completed the new home for award-wining Eastern Kille Spirits in about eleven months.
Facts
Submitter: Wolverine Building Group
Architect: Mathison | Mathison Architects
Size: 14,000 SF
Title: Eastern Kille Distillery
Location: Rockford, MI
Date contract completed: October 2023
Final contract value: $3,575,000
Project manager’s name: Michael Cadieux
Superintendent’s name(s): Howard Gilbert
What percentage of the work scope was self-performed by your company? 75%
The Venue Bella Giornata was a ground-up construction of three buildings totaling approximately 11,000 SF of enchanted venue space. The main building features thrilling sloped ceilings, skylights, rustic cedar beams, and natural finishing materials to enhance the location. The smaller bridal cottage was designed as charming sibling structure.
Facts
Submitter: Wolverine Building Group
Architect: Henrickson Architecture
Size: 11,000 SF
Title: Venue Bella Giornata
Location: Byron Center, MI
Date contract completed: February 2024
Final contract value $3,024,000
Project manager’s name: John Sall
Superintendent’s name(s): Charlie Walker
What percentage of the work scope was self-performed by your company?: 5%
This was a new 16,000 SF grocery store in Holland, MI. The project features high end interior and exterior finishes including such features as a smoothie bar, polished concrete floors, masonry veneer, and many architectural elevation changes on the outside. The inside was designed to keep a smooth flow around the store.
Facts
Submitter: Dykhouse Construction
Architect: Dixon Architecture
Size: 16,000 SF
Title: Harvest Health Foods
Location: Holland, MI
Date contract completed: November 2023
Final contract value $4,395,000
Project manager’s name: Alex Grosvenor
Superintendent’s name(s): Jason Carpenter
What percentage of the work scope was self-performed by your company?: 10%
Custom pre-engineered metal building, serving as new offices and shop space for Dykhouse Construction and Kent Home Services. High end office features include exposed wood truss and glue lam structure, walnut accents and masonry veneer.
Facts
Submitter: Dykhouse Construction
Architect: Dixon Architecture
Size: 17,000 SF
Title: Dykhouse Construction – Office
Location: Wayland, MI
Date contract completed: March 2023
Final contract value $3,150,000
Project manager’s name: Alex Grosvenor
Superintendent’s name(s): Rod Koster
What percentage of the work scope was self-performed by your company?: 15%
Lakewood Construction crafted a healing refuge for Safe Harbor, blending innovative design and strategic planning with community engagement. Overcoming challenges like site suitability and rising costs through value engineering and comprehensive expertise, Lakewood delivered a sustainable environment that serves Safe Harbor’s mission, embodying excellence in construction and community transformation.
Facts
Submitter: Lakewood Construction
Architect: Lakewood Construction
Size: 11,000 SF
Title: Safe Harbor Children’s Advocacy Center
Location: Allegan, MI
Date contract completed: March 2023
Final contract value $2,000,000
Project manager’s name: Kyle Engbers
Superintendent’s name(s): Scott Hatfield
What percentage of the work scope was self-performed by your company?: 20%
First Companies constructed a two-story, 10,000 SF multi-tenant medical office building, maximizing usable land near wetlands. During the winter months, rough framing was completed to deliver this modern medical office building within the client’s timeline. The team made deliberate choices to ensure attractive but distinctive looks for each of the tenants.
The project includes an 11,000 SF building and site improvements, such as parking lots, pickleball courts, a pavilion, a playground, firepit areas, grilling stations, and a pool deck. The building, constructed with structural steel framing, offers leasing offices, a fitness center, co-working spaces, and an open clubhouse room.
Facts
Submitter: CD Barnes Construction
Architect: Progressive Companies
Size: 11,000 SF
Title: Ramblewood Apartments – Clubhouse
Location: Wyoming, MI
Date contract completed: August 2023
Final contract value: $4,749,000
Project manager’s name: Lynne Blondell
Superintendent’s name(s): Jonathan Stoner
What percentage of the work scope was self-performed by your company?: 0%
Pioneer constructed a 20,000 SF clear span, pre-engineered metal hangar for AV Flight at Cherry Capital Airport, featuring a 28 FT x 150 FT track-style door. The 4,000 SF office includes a garage, kitchen, lounge, private offices, and conference rooms with hangar views.
Facts
Submitter: Pioneer Construction
Architect: Bowers+Associates
Size: 23,000 SF
Title: Avflight Traverse City – Hangar
Location: Traverse City, MI
Date contract completed: June 2023
Final contract value: $4,785,000
Project manager’s name: Jon Frego
Superintendent’s name(s): Jeff Cascagnett
What percentage of the work scope was self-performed by your company?: 35%
The Fairlife Project Texas Line 7 was a large-scale production, facilities, and capabilities increase project. The success of this required hundreds of team members and multiple companies’ efforts around continuous design development and workforce flexibility throughout the project to see it to completion.
Facts
Submitter: Van Dyken Mechanical, Inc.
Architect: Ollman Ernest Martin Architects & Engineers
Title: Fairlife – Project Texas Line 7
Location: Coopersville, MI
Date contract completed: February 2024
Final contract value: $18,500,000
Project manager’s name: Jeff Dickman
Superintendent’s name(s): Kyle Hulst
What percentage of the work scope was self-performed by your company?: 90%
The Corewell Health South Parking Deck is home to 1,000 parking spaces for physicians and staff. The precast erection scope included installing 361 architectural precast panels and 13 precast double tees on a seven-level concrete parking deck.
Facts
Submitter: Pioneer Construction
Size: 368,000 SF
Title: Corewell Health – South Parking Deck
Location: Grand Rapids, MI
Date contract completed: March 2024
Final contract value: $3,750,000
Project manager’s name: Dean Hawkins
Superintendent’s name(s): Ken Jones
What percentage of the work scope was self-performed by your company?: 100%