Western Michigan University’s Stadium Club transforms a seasonal suite into a year-round venue for donor engagement and university events. Blending contemporary design, sustainability, and accessibility, the space honors Waldo Stadium’s legacy while supporting the university’s advancement goals with flexible seating, premium finishes, and panoramic views of campus and field.
Facts
Submitter: AVB
Architect: GMB Architecture + Engineering
Size: 3,250 SF
Location: Kalamazoo, MI
Date contract completed: August 2024
Final contract value: $3,600,000
Project manager’s name: Bob Lopez
Superintendent’s name(s): Clay Stull & CJ Noble
What percentage of the work scope was self-performed by your company? 0%
This 4,500 SF addition features performance studios, dressing rooms, and a sundial-inspired red façade. Harlequin spring flooring ensures dancer safety and efficiency, while bold architecture bridges campus styles—mirroring the movement and expression at the heart of Hope College’s thriving dance program.
Facts
Submitter: Lakewood Construction
Architect: HGA
Size: 4,500 SF
Location: Holland, MI
Date contract completed: October 2024
Final contract value: $4,000,000
Project manager’s name: Kyle Vyncke
Superintendent’s name(s): Steve Weatherwax
What percentage of the work scope was self-performed by your company? 4%
Pioneer Construction completed a $7 million interior renovation at Gun Lake Casino, transforming three areas into a new bar and lounge, a high-limit gaming room, and the Lucky Dragon Noodle Bar—all within an active casino environment and in coordination with a concurrent major expansion.
Peace Church underwent a redesign and expansion of their campus. Our team assisted Peace Church in documenting their needs and developing a plan to accommodate their growth. One of the goals for this project was to expand the sanctuary from 600 seats to now 1,200 seats.
Facts
Submitter: Dan Vos Construction Company
Architect: Dan Vos Construction Company
Size: 22,700 SF
Location: Middleville, MI
Date contract completed: April 2025
Final contract value: $8,700,000
Project manager’s name: Jameson DeBlaay
Superintendent’s name(s): Todd Cooper
What percentage of the work scope was self-performed by your company? 21%
West Pharmaceutical Services was looking to add an addition to their manufacturing building in 2023. Langerak Roof Systems was called in to install over 34,000 SF of roofing. This project took approximately 11 months, from August of 2023 to July of 2024.
Facts
Submitter: Langerak Roof Systems, Inc.
Architect: Alliance Architects
Size: 34155 SF
Title: West Pharmaceutical Services
Location: Walker, MI
Date contract completed: July 2024
Final contract value: $477,000
Project manager’s name: Lucas Langerak
Superintendent’s name(s): Craig Pantelin
What percentage of the work scope was self-performed by your company? 92%
The Kendall College of Art & Design project faced numerous challenges in the latest collaboration between Ferris State University, consultant Kenn Krum, and Great Lakes Systems. Leveraging relationship strengths such as meticulous planning, effective communication, and attention to detail, the team successfully delivered a high-quality project that surpassed Ferris State’s expectations.
Facts
Submitter: Great Lakes Systems
Architect: RoofTech
Size: 23890 SF
Title: Ferris State University — Kendall College of Art & Design
Location: Grand Rapids, MI
Date contract completed: October 2024
Final contract value: $739,000
Project manager’s name: Jeff Myers
Superintendent’s name(s): John Steffes
What percentage of the work scope was self-performed by your company? 100%
Buist Sheet Metal fabricated and installed a traditional double locked standing seam metal roof, providing protection from the elements for the second 85 years of this Holland icon. The rebuilt Ottawa Beach General Store mimics the historic building that was replaced and features clean lines across hips and slope changes.
Facts
Submitter: Buist Sheet Metal
Architect: Dixon Architecture
Size: 4000 SF
Title: Ottawa Beach General Store
Location: Holland, MI
Date contract completed: April 2024
Final contract value: $85,000
Project manager’s name: Joe Feldpausch
Superintendent’s name(s): Jesse Emelander, Jose Ruelas, & Sam Rice
What percentage of the work scope was self-performed by your company? 97%
This luxury apartment complex features 12 wood-framed buildings, a clubhouse, 13 garages, and premium amenities. Constructed with high-end materials and smart technology, the project overcame poor soils, supply delays, and complex scheduling. Strategic phasing, quality controls, and thoughtful design ensured a successful, modern community, built for lasting comfort.
Facts
Submitter: CD Barnes Construction
Architect: Ghafari Associates
Location: Grandville, MI
Date contract completed: December 2024
Final contract value: $77,365,000
Project manager’s name: Thomas Berry & John Maycroft
Superintendent’s name(s): Aaron Roberts, Tom Minnema, & Ty Langlois
What percentage of the work scope was self-performed by your company? 0%
Hudsonville High School and Freshman Campus is a project that involved tall cast in place concrete walls, foundation, flatwork, sitework and polished concrete. The jobsite was tight and the schedule was precise. There was not one side of the school that was left without new concrete placed inside and out.
Facts
Submitter: Burgess Concrete Construction
Architect: GMB Architecture + Engineering
Size: 148,940 SF
Location: Hudsonville, MI
Date contract completed: October 2024
Final contract value: $3,737,000
Project manager’s name: Matt Burgess & Al Jeurink
Superintendent’s name(s): Matt Burgess & Jordan Burgess
What percentage of the work scope was self-performed by your company? 97.3%
U-Haul is a three-story storage facility designed with extensive reinforced concrete from the below-grade footings and walls up to the suspended level one slab to maintain the building’s structural integrity. This was a larger-scale concrete structure requiring knowledge, experience, large equipment, and a lot of manpower.
Facts
Submitter: Burgess Concrete Construction
Architect: Comprehensive Engineering
Size: 20,000 SF
Location: Walker, MI
Date contract completed: October 2024
Final contract value: $1,323,000
Project manager’s name: Joe Hunderman
Superintendent’s name(s): Tony Dykhouse & John Rogers
What percentage of the work scope was self-performed by your company? 99.7%