DeVries Jewelers

Story

DeVries Jewelers is a local business that was looking to update their facility in the historic district of Grand Rapids. Kleyn Electric was instrumental in designing and building a new ground up facility that integrated updated security and technology while maintaining the historic charm of downtown Grand Rapids.

Facts

Submitter: Kleyn Electric Inc.

Size: 6,270 SF

Location: Grand Rapids

Date contract completed: December 2024

Final contract value: $231,000

Project manager’s name: Ryan Kooinga

Superintendent’s name(s): Kevin Kuiper

What percentage of the work scope was self-performed by your company? 96%

Pro Star Aviation

Story

HighPoint completed a ground-up build for Pro Star Aviation, providing full electrical design, access control, security, utility relocation, and a new taxiway with lighting and signage—all within an active airport. The project demanded precise coordination, safety compliance, and seamless integration with ongoing airport operations.

Facts

Submitter: HighPoint

Architect: Bowers+Associates

Location: Grand Rapids

Date contract completed: December 2024

Final contract value: $999,600

Project manager’s name: Joe Hailk

Superintendent’s name(s): Tyler Aungst

What percentage of the work scope was self-performed by your company? 100%

West Ottawa Public Schools — Performing Arts Center

Story

Town & Country Group coordinated all of the installations of raceways, wiring, and rough-ins for all systems that required wires. Balancing design needs and engineered needs, Town & Country professionals maintained a quality finish with functionality all the way to the end.

Facts

Submitter: Town & Country Group

Architect: GMB Architecture + Engineering

Size: 56,000 SF

Location: Holland, MI

Date contract completed: May 2024

Final contract value: $2,700,000

Project manager’s name: Jeff Jipping

Superintendent’s name(s): Jacob Woudwyk

What percentage of the work scope was self-performed by your company? 95%

Gun Lake Tribal Gaming Authority — Wastewater Treatment Facility

Story

This was the new construction of the Wastewater Treatment Facility for Gun Lake Casino where Hillard Electric preformed the complete electrical installation.

Facts

Submitter: Hillard Electric

Architect: Fishbeck

Location: Wayland, MI

Date contract completed: May 2025

Final contract value: $3,160,000

Project manager’s name: John Wood

Superintendent’s name(s): Colton Newton

What percentage of the work scope was self-performed by your company? 100%