SecurAlarm’s work on the Concourse A expansion project at Gerald R. Ford International Airport included fire alarm system upgrades and advanced security integrations, enhancing safety and efficiency. The team overcame complex system transitions and airport constraints to deliver seamless, code-compliant solutions supporting future passenger growth.
Facts
Submitter: SecurAlarm
Location: Grand Rapids, MI
Date contract completed: February 2024
Final contract value: $1,901,677
Project manager’s name: Dorrell Priest
Superintendent’s name(s): Brian Lomonaco & Chris Kaminski
What percentage of the work scope was self-performed by your company? 80%
Feyen Zylstra provided comprehensive low-voltage cabling services for Corewell Health Place, a new 300,000 SF office hub located in Grand Rapids, MI. FZ provided the network and security systems, fiber optic backbone, and IT infrastructure, ensuring a secure operational environment for Corewell Health’s future needs.
Facts
Submitter: Feyen Zylstra, LLC
Architect: Corewell Health
Size: 300,000 SF
Location: Grand Rapids, MI
Date contract completed: November 2024
Final contract value: $548,752
Project manager’s name: Randy Jacobusse
Superintendent’s name(s): Chad Jansma
What percentage of the work scope was self-performed by your company? 100%
Feyen Zylstra provided the complete low-voltage cabling package for Corewell Health’s new 12-story patient care building. The extensive network, security, and communication cabling services FZ provided will ensure efficient and secure operations for years to come.
Facts
Submitter: Feyen Zylstra, LLC
Architect: Corewell Health
Size: 240,000 SF
Location: Grand Rapids, MI
Date contract completed: March 2025
Final contract value: $1,029,096
Project manager’s name: Randy Jacobusse
Superintendent’s name(s): Justin Anderson
What percentage of the work scope was self-performed by your company? 100%
Buist provided low-voltage services for the new 96-bed, 72,000 SF Southridge Behavioral Hospital in Byron Center. The scope of work included structured cabling, access control, surveillance, and fiber infrastructure to support the hospital’s $46,000,000 facility, which opened in March 2025 and employs 170 medical professionals.
Facts
Submitter: Buist Electric
Architect: Stengel Hill
Title: UHS & Trinity Health MI — Southridge Behavioral Hospital
Size: 96 SF
Location: Byron Center, MI
Date contract completed: March 2025
Final contract value: $717,581
Project manager’s name: Jason Williams
Superintendent’s name(s): Derek Cass
What percentage of the work scope was self-performed by your company? 100%