Pine Rest Pediatric Center of Behavioral Health

Story

Pine Rest’s pediatric hospital required security that protects vulnerable patients while preserving a calm, welcoming environment. Working with Windemuller and Pine Rest, SecurAlarm delivered integrated fire, access, video, key management, and personal panic systems that strengthen staff confidence, support care delivery, and create a reassuring experience for patients and families.

Facts

Submitter: SecurAlarm Systems, inc.

Size: 160,000 SF

Location: Grand Rapids, MI

Date contract completed: March 2026

Final contract value: $856,000

Project manager’s name: Dorrell Priest

Superintendent’s name(s): Brian Lomonaco, Logan Pillsbury

What percentage of the work scope was self-performed by your company? 20%

City of Grand Rapids — Public Service Center

Story

Network cabling infrastructure, Network cabling, Optical Fiber, and network racking as well as access control infrastructure. 30,000 feet of Cat 6A, 15,000 feet Access Control Cabling and 8,000 feet of Optical Fiber

Facts

Submitter: Hillard Electric

Architect: Colliers, Geotech

Size: 323,290 SF

Location: Grand Rapids, MI

Date contract completed: November 2025

Final contract value: $676,000

Project manager’s name: Hudson Ruhlig

Superintendent’s name(s): Reed Willmore

What percentage of the work scope was self-performed by your company? 75%

CS Erickson Headquarters

Story

CS Erickson installed the complete structured cabling and technology infrastructure for its 19,000 SF Hub 1 headquarters in Grand Rapids. The project features organized network racks, fiber backbone connectivity, overhead cable-tray pathways, and integrated audiovisual systems that support collaboration spaces, training environments, and modern workplace connectivity.

Facts

Submitter: CS Erickson

Size: 19,000 SF

Location: Grand Rapids, MI

Date contract completed: April 2025

Final contract value: $50,000

Project manager’s name: Drew Guy

Superintendent’s name(s): Tad Dobre

What percentage of the work scope was self-performed by your company? 100%

Calvin Theological Seminary — 3300 Apartments

Story

Grand Valley Automation installed a complete DDC building automation system for a new four-story student housing facility at Calvin Theological Seminary. Through extensive preplanning and coordination, the team successfully navigated fire-rated construction challenges to deliver reliable HVAC controls for the residential building.

Facts

Submitter: Grand Valley Automation, Inc.

Location: Grand Rapids, MI

Date contract completed: October 2025

Final contract value: $251,000

Project manager’s name: Nick Crandell

Superintendent’s name(s): Keith Krausbauer

What percentage of the work scope was self-performed by your company? 100%

Covenant Christian High School

Story

Grand Valley Automation delivered a fully engineered building automation system for the Covenant Christian High School addition, integrating advanced environmental controls, specialized lab ventilation, and safety systems to provide optimal comfort and a safe learning environment for students and staff.

Facts

Submitter: Grand Valley Automation, Inc.

Architect: The Design Forum

Location: Walker, MI

Date contract completed: April 2026

Final contract value: $279,500

Project manager’s name: Matt Salvati

Superintendent’s name(s): Cody Hughes

What percentage of the work scope was self-performed by your company? 100%

Benteler Automotive

Story

Buist delivered a comprehensive communications infrastructure for Benteler Automotive’s new 315,000 SF Stafford Plant in Grand Rapids. The team installed structured cabling, fiber backbone, wireless systems, surveillance, and access control to support secure, facility-wide connectivity. This work ensures the plant is fully equipped for efficient operations and long-term production needs.

Facts

Submitter: Buist Electric

Architect: Lakewood Construction

Location: Wyoming, MI

Date contract completed: March 2026

Final contract value: $189,000

Project manager’s name: Lupe Martinez

Superintendent’s name(s): Hunter Ruhlig

What percentage of the work scope was self-performed by your company? 100%

Amway Corporation — The Commons

Story

Feyen Zylstra partnered with Amway to modernize administrative spaces at Amway’s Global Headquarters in Ada, Michigan. The project upgraded offices, collaboration areas, and IT infrastructure, including fiber backbone, wireless access points, and security systems. Rigorous testing and coordination ensured seamless integration, supporting Amway’s long-term success.

Facts

Submitter: Feyen Zylstra

Location: Ada, MI

Date contract completed: March 2025

Final contract value: $376,000

Project manager’s name: Terry Finch

Superintendent’s name(s): Mark Scobey

What percentage of the work scope was self-performed by your company? 100%