WINNER: West Michigan Beef Company – Processing Facility

Story

Putting Together a Giant Puzzle: The project team was challenged with assembling and suspending an immense weight of specialized beef processing equipment. West Michigan Beef imported a piece of one-of-a-kind beef equipment from the Netherlands. Borrowing the concept they implemented for another local food producer, the team custom-built the equipment support system from secondary steel.

Facts

Submitter: Dan Vos Construction Company

Architect: Dan Vos Construction Company

Size: 90,000 SF

Title: West Michigan Beef Company – Processing Facility

Location: Hudsonville, MI

Date contract completed: January 2023

Final contract value: $35,070,000

Project manager’s name: Daryl Johnson

Superintendent’s name(s): Chris Barry

What percentage of the work scope was self-performed by your company? 11%