South Christian High School welcomed its largest incoming class ever, prompting a north wing expansion with 12 new classrooms to enhance general and inclusive learning. Built with precast concrete panels, the fast-paced project required careful coordination due to its location and winter construction conditions.
Facts
Submitter: Dan Vos Construction Company
Architect: AMDG Architects
Location: Byron Center, MI
Date contract completed: January 2025
Final contract value: $79,000
Project manager’s name: Jameson DeBlaay, Aaron Raha
Superintendent’s name(s): Max Stormzand, Matt Danders
What percentage of the work scope was self-performed by your company? 100%
As the precast erector for GVSU’s Lubbers Stadium project, Pioneer installed 82 structural planks—some over 25,000 pounds—despite tight access and a compressed summer schedule. Precision lifts and coordinated execution ensured the scope was completed safely and on time for the football season opener.
The Corewell Health South Parking Deck is home to 1,000 parking spaces for physicians and staff. The precast erection scope included installing 361 architectural precast panels and 13 precast double tees on a seven-level concrete parking deck.
Facts
Submitter: Pioneer Construction
Size: 368,000 SF
Title: Corewell Health – South Parking Deck
Location: Grand Rapids, MI
Date contract completed: March 2024
Final contract value: $3,750,000
Project manager’s name: Dean Hawkins
Superintendent’s name(s): Ken Jones
What percentage of the work scope was self-performed by your company?: 100%