This highly specialized distillation rack will convert dairy byproduct into 2.3 million gallons of ethanol fuel annually, supporting renewable energy and reducing environmental impact. Despite complex logistics and harsh winter conditions, the skilled seven-person crew completed installation in just 21 days.
Facts
Submitter: Dan Vos Construction Company
Architect: Praj Industries
Size: 3,600 SF
Location: Constantine, MI
Date contract completed: January 2026
Final contract value: $700,000
Project manager’s name: Jeff Boot, Aaron Raha
Superintendent’s name(s): Brad Ellens, Matt Danders
What percentage of the work scope was self-performed by your company? 100%
Pioneer Construction coordinated erection of the 3,130-ton steel canopy and outhouses at the Acrisure Amphitheater, spanning roughly 60,000 SF. Work included connection detailing, equipment planning, shoring tower coordination, and erection sequencing.
Facts
Submitter: Pioneer Construction
Architect: Progressive Companies
Location: Grand Rapids, MI
Date contract completed: July 2025
Final contract value: $5,542,000
Project manager’s name: Warren Potter
Superintendent’s name(s): Twig Terwilliger, Mike Herweyer
What percentage of the work scope was self-performed by your company? 100%
Wolverine completed a 147,000 SF manufacturing facility for Rollon® by Timken, designed to produce linear motion systems. The facility includes custom machining mill foundations, loading docks, and office spaces with natural lighting. The project was finished within a nine-month schedule to meet production goals.
Pioneer Construction completed the structural steel erection for the Pine Rest Pediatric Center of Behavioral Health, a 136,000 SF facility in Grand Rapids. The multi-wing design required careful crane coordination and close collaboration with other trades to meet schedule demands while maintaining safety and precision on site.
Facts
Submitter: Pioneer Construction
Architect: BWBR
Size: 136,000 SF
Location: Grand Rapids, MI
Date contract completed: November 2024
Final contract value: $479,000
Project manager’s name: Warren Potter
Superintendent’s name(s): Dan Smith
What percentage of the work scope was self-performed by your company? 100%
Pioneer Construction erected 20 tons of structural steel for the Grand Rapids Public Museum’s expansion. Tight access near the Grand River demanded careful coordination, but Pioneer’s team delivered on schedule, supporting a major investment in community, accessibility, and the future of this landmark cultural destination.
Facts
Submitter: Pioneer Construction
Architect: TowerPinkster
Size: 10,000 SF
Location: Grand Rapids, MI
Date contract completed: October 2024
Final contract value: $150,000
Project manager’s name: Dean Hawkins
Superintendent’s name(s): Mike Herweyer
What percentage of the work scope was self-performed by your company? 100%
FCC Construction, selected for its structural steel expertise, successfully delivered an exceptional hangar project that surpassed expectations. With complex heavy steelwork spanning 125 FT, a 300-ton crane ensured ample capacity. Despite challenges such as airport logistics, safety remained paramount, with zero injuries recorded during the 8,000 self-performed labor hours.
Facts
Submitter: FCC Construction Inc.
Architect: Integrated Architecture
Size: 40,000 SF
Title: Otter Air Services – Hangar & Corporate Office
Location: Grand Rapids, MI
Date contract completed: September 2023
Final contract value: $2,500,000
Project manager’s name: Mark Deblaay
Superintendent’s name(s): Todd Kortenhoven
What percentage of the work scope was self-performed by your company?: 100%
The HT Hackney Company dry-goods and freezer addition is a design/build multi-phase expansion. Technically advanced 16 truck bays replace and expand shipping and receiving capacity. Employee areas feature lockers, restrooms and offices.
Facts
Submitter: Dan Vos Construction Company
Architect: Dan Vos Construction Company
Size: 120,000 SF
Title: H.T. Hackney
Location: Wyoming, MI
Date contract completed: March 2024
Final contract value: $21,941,000
Project manager’s name: Jeff Boot
Superintendent’s name(s): Nick Rempalski
What percentage of the work scope was self-performed by your company?: 8%
Pioneer Construction erected approximately 2,000 tons of steel for Corewell Health’s new twelve-story ambulatory building which includes a four-story connector bridge.
Facts
Submitter: Pioneer Construction
Title: Corewell Health – Ambulatory Building
Location: Grand Rapids, MI
Date contract completed: November 2023
Final contract value: $1,700,000
Project manager’s name: Warren Potter
Superintendent’s name(s): Dan Smith
What percentage of the work scope was self-performed by your company?: 100%