City of Grand Rapids — Amphitheater Parking

The construction of City of Grand Rapids — Amphitheater Parking

Story

The Acrisure Parking Ramp included erection of 461 precast pieces, some weighing up to 85,000 pounds. Despite a tight site with no laydown area, 282 truckloads were efficiently coordinated. Using a strategically placed 330-ton crawler crane, the team completed erection in 42 days with minimal weather delays.

Facts

Submitter: Pioneer Construction

Architect: Progressive Companies

Location: Grand Rapids, MI

Date contract completed: July 2025

Final contract value: $6,710,000

Project manager’s name: Dean Hawkins

Superintendent’s name(s): Kenny Jones, John Morris

What percentage of the work scope was self-performed by your company? 100%