Story
The Acrisure Parking Ramp included erection of 461 precast pieces, some weighing up to 85,000 pounds. Despite a tight site with no laydown area, 282 truckloads were efficiently coordinated. Using a strategically placed 330-ton crawler crane, the team completed erection in 42 days with minimal weather delays.
Facts
Submitter: Pioneer Construction
Architect: Progressive Companies
Location: Grand Rapids, MI
Date contract completed: July 2025
Final contract value: $6,710,000
Project manager’s name: Dean Hawkins
Superintendent’s name(s): Kenny Jones, John Morris
What percentage of the work scope was self-performed by your company? 100%