Acrisure Amphitheater

Story

The crew laid over 55,000 eight-inch CMU blocks to construct robust stair and elevator shafts, backstage areas, and a 300-foot-long fire wall for a premier concert venue. Working efficiently on an accelerated timeline, the team installed more than 45,000 SF of stone across the facility. This extensive masonry work featured 1,600 SF of hand-split radius stone, ultimately delivering a timeless full-stone veneer that creates a welcoming, visually striking atmosphere for concert-goers.

Facts

Submitter: Integrated Exteriors

Architect: Progressive Companies

Location: Grand Rapids, MI

Date contract completed: March 2026

Final contract value: $4,467,000

Project manager’s name: Jeff Schipper

Superintendent’s name(s): Scott Donze

What percentage of the work scope was self-performed by your company? 95%