DeWys Metal Solutions, a locally owned sheet metal fabricator and manufacturing company, nearly tripled the size of their Marne, MI, headquarters with this expansion and renovation. The added space houses a C-suite to consolidate DeWys’ leadership team, as well as new conference rooms and upgraded work stations.
Facts
Submitter: Wolverine Building Group
Architect: Wolverine Building Group
Size: 12,000 SF
Location: Marne, MI
Date contract completed: August 2024
Final contract value: $4,700,000
Project manager’s name: Mike Beuschel
Superintendent’s name(s): Howard Gilbert
What percentage of the work scope was self-performed by your company? 20%
Erhardt transformed a former college building into the Children’s Healing Center’s new headquarters, creating a safe, engaging space for immunocompromised children. The project included renovated play areas, a gym, café, and offices, with a hospital-grade HVAC system ensuring clean air. Early collaboration ensured a smooth design-build process.
Facts
Submitter: Erhardt Construction
Architect: Diekema Hamann
Size: 15,000 SF
Location: Grand Rapids, MI
Date contract completed: September 2024
Final contract value: $4,800,000
Project manager’s name: Taggart Town
Superintendent’s name(s): Doug O’Dell
What percentage of the work scope was self-performed by your company? 13%
Peace Church underwent a redesign and expansion of their campus. Our team assisted Peace Church in documenting their needs and developing a plan to accommodate their growth. One of the goals for this project was to expand the sanctuary from 600 seats to now 1,200 seats.
Facts
Submitter: Dan Vos Construction Company
Architect: Dan Vos Construction Company
Size: 22,700 SF
Location: Middleville, MI
Date contract completed: April 2025
Final contract value: $8,700,000
Project manager’s name: Jameson DeBlaay
Superintendent’s name(s): Todd Cooper
What percentage of the work scope was self-performed by your company? 21%
Pioneer Construction completed a $7 million interior renovation at Gun Lake Casino, transforming three areas into a new bar and lounge, a high-limit gaming room, and the Lucky Dragon Noodle Bar—all within an active casino environment and in coordination with a concurrent major expansion.
Buist Sheet Metal fabricated and installed a traditional double locked standing seam metal roof, providing protection from the elements for the second 85 years of this Holland icon. The rebuilt Ottawa Beach General Store mimics the historic building that was replaced and features clean lines across hips and slope changes.
Facts
Submitter: Buist Sheet Metal
Architect: Dixon Architecture
Size: 4000 SF
Title: Ottawa Beach General Store
Location: Holland, MI
Date contract completed: April 2024
Final contract value: $85,000
Project manager’s name: Joe Feldpausch
Superintendent’s name(s): Jesse Emelander, Jose Ruelas, & Sam Rice
What percentage of the work scope was self-performed by your company? 97%
The Kendall College of Art & Design project faced numerous challenges in the latest collaboration between Ferris State University, consultant Kenn Krum, and Great Lakes Systems. Leveraging relationship strengths such as meticulous planning, effective communication, and attention to detail, the team successfully delivered a high-quality project that surpassed Ferris State’s expectations.
Facts
Submitter: Great Lakes Systems
Architect: RoofTech
Size: 23890 SF
Title: Ferris State University — Kendall College of Art & Design
Location: Grand Rapids, MI
Date contract completed: October 2024
Final contract value: $739,000
Project manager’s name: Jeff Myers
Superintendent’s name(s): John Steffes
What percentage of the work scope was self-performed by your company? 100%
West Pharmaceutical Services was looking to add an addition to their manufacturing building in 2023. Langerak Roof Systems was called in to install over 34,000 SF of roofing. This project took approximately 11 months, from August of 2023 to July of 2024.
Facts
Submitter: Langerak Roof Systems, Inc.
Architect: Alliance Architects
Size: 34155 SF
Title: West Pharmaceutical Services
Location: Walker, MI
Date contract completed: July 2024
Final contract value: $477,000
Project manager’s name: Lucas Langerak
Superintendent’s name(s): Craig Pantelin
What percentage of the work scope was self-performed by your company? 92%
This luxury apartment complex features 12 wood-framed buildings, a clubhouse, 13 garages, and premium amenities. Constructed with high-end materials and smart technology, the project overcame poor soils, supply delays, and complex scheduling. Strategic phasing, quality controls, and thoughtful design ensured a successful, modern community, built for lasting comfort.
Facts
Submitter: CD Barnes Construction
Architect: Ghafari Associates
Location: Grandville, MI
Date contract completed: December 2024
Final contract value: $77,365,000
Project manager’s name: Thomas Berry & John Maycroft
Superintendent’s name(s): Aaron Roberts, Tom Minnema, & Ty Langlois
What percentage of the work scope was self-performed by your company? 0%
Hastings Streetscape is a downtown revitalization project enhancing sidewalks, crosswalks, and public spaces. Kent placed over 48,000 SF of standard, colored, and exposed aggregate concrete, along with curbs, planter foundations, and more. Through strategic sequencing and real-time coordination, the result is a beautiful streetscape delivered without disruptions to downtown businesses.
Facts
Submitter: Kent Companies, Inc.
Size: 48,390 SF
Location: Hastings, MI
Date contract completed: August 2024
Final contract value: $800,000
Project manager’s name: Kevin Arevalo
Superintendent’s name(s): Blane Lester
What percentage of the work scope was self-performed by your company? 100%
Kent Concrete delivered full building and site concrete packages for the new Sunbelt Rentals in Traverse City. The scope included footings, slabs, bollards, curbs, paving, and a custom wash bay. Coordination with the excavators ensured seamless execution, efficient sequencing, and high-quality finishes across more than 1,000 CY of concrete.
Facts
Submitter: Kent Companies, Inc.
Architect: NORR
Size: 65,000 SF
Location: Traverse City, MI
Date contract completed: October 2024
Final contract value: $622,000
Project manager’s name: Cassidy Lennerth
Superintendent’s name(s): Tony Kenner & Clayton Schlotterbeck
What percentage of the work scope was self-performed by your company? 100%