The Grand Rapids City Services Office and Garage project successfully modernized and consolidated critical municipal operations into a centralized campus. The completed facility provides enhanced office and operational space, expanded fleet maintenance capabilities, resilient emergency infrastructure, and significant support for the City’s growing electric vehicle fleet through the installation of eighteen (18) EV charging stations located throughout the campus.
Facts
Submitter: Allied Electric Inc
Architect: Bergman
Location: Grand Rapids, MI
Date contract completed: March 2026
Final contract value: $4,171,000
Project manager’s name: Percy Haywood
Superintendent’s name(s): Jordan Gilbert
What percentage of the work scope was self-performed by your company? 100%