Dan’s Excavating reconstructed Fremont Street by replacing the aging sanitary sewer, water services, and storm drainage while rebuilding the roadway from the ground up. The scope of work included removals, new utilities, aggregate base, asphalt paving, curb and gutter, sidewalks, and restoration. These comprehensive upgrades successfully improved infrastructure reliability, drainage, and long-term roadway performance for the community.
Facts
Submitter: Dan’s Excavating Service, Inc.
Location: Rockford, MI
Date contract completed: September 2025
Final contract value: $454,000
Project manager’s name: Spencer Tellkamp
Superintendent’s name(s): Griffin Reed
What percentage of the work scope was self-performed by your company? 90%