Story
Located within the restricted AOA of Gerald R. Ford International Airport, this project required careful coordination, especially for concrete and asphalt work. Close proximity to the runway and collaboration with the FAA and Air Traffic Control added complexity. Despite challenges, the project was completed on time and on budget.
Facts
Submitter: FCC Construction Inc.
Architect: DLZ
Title: Gerald R. Ford International Airport — Snow Removal Equipment Building
Size: 60,000 SF
Location: Kentwood, MI
Date contract completed: October 2024
Final contract value: $7,350,000
Project manager’s name: James Zehr
Superintendent’s name(s): Nick Dent
What percentage of the work scope was self-performed by your company? 30%