John Ball Zoo — Boardwalk

Excellence in Construction Awards

Story

The John Ball Zoo Boardwalk connects the chimpanzee plaza to the zoo’s new African expansion along a steep wooded hillside. Built with more than 20,000 feet of wood decking and minimal tree removal, the elevated structure required careful material handling, continuous fall protection, and precise carpentry throughout construction.

Facts

Submitter: Triangle Constructors

Architect: Classic Engineering

Location: Grand Rapids, MI

Date contract completed: April 2026

Final contract value: $651,000

Project manager’s name: Steve Johnson

Superintendent’s name(s): Adam Buys

What percentage of the work scope was self-performed by your company? 95%