Ferris State University’s Center for Virtual Learning brings together their most innovative academic programs with advanced facilities, emerging technologies, and innovative classrooms. The facility houses the Digital Media, Information Security and Intelligence, Digital Animation, and Game Design programs, and is home to the state’s only purpose-built E-Sports arena.
Facts
Submitter: Triangle Associates
Architect: Stantec
Size: 64,000 SF
Title: Ferris State University – Center for Virtual Learning
Location: Big Rapids, MI
Date contract completed: August 2023
Final contract value: $24,300,000
Project manager’s name: Matt Novak
Superintendent’s name(s): Bob Lackey
What percentage of the work scope was self-performed by your company? 0%
Hampton Inn & Suites Manistee Waterfront offers direct Lake Michigan access. This five-story hotel features 102 rooms with lake-view balconies, a beach bar, firepits, and a top-floor restaurant. Amenities include a fitness center, indoor pool, hot tub, EV charging, and remarkable sunsets.
Facts
Submitter: Pioneer Construction
Architect: Ghafari Associates
Size: 70,000 SF
Title: Hampton Inn & Suites Manistee Waterfront
Location: Manistee, MI
Date contract completed: June 2023
Final contract value: $21,000,000
Project manager’s name: Justin Bialik
Superintendent’s name(s): Phil Geurink
What percentage of the work scope was self-performed by your company? 15%
Putting Together a Giant Puzzle: The project team was challenged with assembling and suspending an immense weight of specialized beef processing equipment. West Michigan Beef imported a piece of one-of-a-kind beef equipment from the Netherlands. Borrowing the concept they implemented for another local food producer, the team custom-built the equipment support system from secondary steel.
Facts
Submitter: Dan Vos Construction Company
Architect: Dan Vos Construction Company
Size: 90,000 SF
Title: West Michigan Beef Company – Processing Facility
Location: Hudsonville, MI
Date contract completed: January 2023
Final contract value: $35,070,000
Project manager’s name: Daryl Johnson
Superintendent’s name(s): Chris Barry
What percentage of the work scope was self-performed by your company? 11%
This project consisted of five buildings, totaling 170,000 SF. Each building had its own schedule with overlap. Most of the eight-inch floors sloped to drains and were placed on insulation for in-floor heat. Building flatwork, foundations and excavations of footings was the entire scope.
Facts
Submitter: Van Laan Concrete Construction
Size: 170,000 SF
Title: Road Commission of Kalamazoo County – Phase II
Location: Kalamazoo, Michigan
Date contract completed: February 2024
Final contract value: $3,825,000
Project manager’s name: Josh Van Laan
Superintendent’s name(s): Ben Hildebrand
What percentage of the work scope was self-performed by your company? 95%
Impact Dynamic Training’s mission is “to provide mindful teaching and coaching to each individual athlete while enhancing their skills and building relationships in the process.” This new facility serves as the company’s headquarters and provides an inviting environment where volleyball and pickleball communities can gather for support, encouragement, and fun.
Facts
Submitter: Veneklasen Construction
Architect: Andrus Architecture
Size: 36,000 SF
Title: Impact Dynamic Training
Location: Hudsonville, MI
Date contract completed: March 2023
Final contract value: $3,432,000
Project manager’s name: Cody Klomes
Superintendent’s name(s): Kasey Chubb
What percentage of the work scope was self-performed by your company? 35%
This project consisted of a new vehicle maintenance building, an addition to existing hangar, and a new main hangar featuring a 230 FT clearspan and additional space for office and storage.
Facts
Submitter: Pioneer Construction
Architect: Tectonic Management Group
Size: 74,000 SF
Title: Duncan Aviation
Location: Battle Creek, MI
Date contract completed: February 2024
Final contract value: $11,326,000
Project manager’s name: Adam Wheeler
Superintendent’s name(s): Drake Walker, Steve Suchowian, Danny Clayton
What percentage of the work scope was self-performed by your company? 100%
The New Holland Brewing Battle Creek location includes an inviting outdoor beer garden that seamlessly integrates with the existing brick structure of the main building. Situated in the heart of Battle Creek, coordinating deliveries and staging materials posed logistical challenges due to the limited space. The team had to use an off-site laydown area as they couldn’t stage much within the building footprint. The building itself showcases beautiful architectural finishes, including a standing seam roof and a ceiling liner panel.
Facts
Submitter: Pioneer Construction
Architect: J. Andrew Baer Architect
Size: 4,000 SF
Title: New Holland Brewing – Battle Creek Brewpub
Location: Battle Creek, MI
Date contract completed: January 2023
Final contract value: $3,165,000
Project manager’s name: Adam Wheeler
Superintendent’s name(s): Drake Walker
What percentage of the work scope was self-performed by your company? 100%
Ada Village – A3 Building was the first contract in a large section of buildings and this building became a restaurant. The work on this project included an elevator shaft, firewall, stairwell, and brick veneer. The team used EZ Scaffold to help complete this project. This project had its challenges with tight working spaces due to the location, number of different mortar and brick colors and arches.
Facts
Submitter: Kortman Masonry
Title: Ada Village – A3 Building
Location: Ada, MI
Date contract completed: May 2023
Final contract value: $345,000
Project manager’s name: Nick Kortman
Superintendent’s name(s): Aaron Reichert
What percentage of the work scope was self-performed by your company? 100%
Family Church purchased the old Huntington Bank Headquarters located in Holland for additional space. The first phase of construction at this location will include a new fellowship area, additional areas for kids, ministries, and offices for church administration.
Facts
Submitter: CarbonSix Construction
Architect: Gen1 Architectural Group
Size: 140,000 SF
Title: Family Church – Redwood Campus
Location: Holland, MI
Date contract completed: September 2023
Final contract value: $4,248,000
Project manager’s name: Jonathan Mattson
Superintendent’s name(s): Corey Hall
What percentage of the work scope was self-performed by your company? 20%
Amway had a vision to transform its World Headquarters into a modern-day innovation hub. The central hub between three main corridors and features a coffee bar, flexible, collaborative meeting space and conference rooms, along with areas that support independent work.
Facts
Submitter: Rockford Construction
Architect: Progressive Companies
Size: 16,000 SF
Title: Amway Treehouse
Location: Ada, MI
Date contract completed: September 2023
Final contract value: Undisclosed
Project manager’s name: Aaron Ebnit, Steve McGovern