The entire project covered 90,000 SF, it began in the fall and continued through the winter months. Besides, most of the walls were tall, radiused, and had multiple elevations, difficult to form. The freezer floors were placed on insulation and had hardener broadcast into the surface. The team was challenged by ten different USDA curb wall section details, totaling over half a mile in length.
Facts
Submitter: Van Laan Concrete Construction
Size: 90,000 SF
Title: West Michigan Beef Company – Processing Facility
Location: Hudsonville, MI
Date contract completed: January 2024
Final contract value: $1,600,000
Project manager’s name: Josh Van Laan
Superintendent’s name(s): Keegan Forman, Terry Jordan
What percentage of the work scope was self-performed by your company?: 100%
Kent Companies masterfully designed and built the lodge entrance at Shanty Creek. Work consisted of walls to frame the building, steps and caps, core drilled railings, and integral coloring and stamping to complement the natural lumber.
Facts
Submitter: Kent Companies
Architect: Performance Engineers
Size: 18,000 SF
Title: Shanty Creek Resort – Lodge Entrance
Location: Bellaire, Michigan
Date contract completed: September 2023
Final contract value: $218,000
Project manager’s name: Jason Harrall
Superintendent’s name(s): Tony Kenner, Clayton Schlotterbeck
What percentage of the work scope was self-performed by your company? : 100%
Kent Companies built this 17-story multifamily structure on a zero lot line site with the use of the Doka Safety Wall system. Studio Park Tower is the fifth-tallest building in the city and built atop an existing six-level parking structure.
Facts
Submitter: Kent Companies
Architect: Integrated Architecture
Size: 224,000 SF
Title: Studio Park Tower
Location: Grand Rapids, Michigan
Date contract completed: April 2024
Final contract value: $10,400,000
Project manager’s name: Steve McCoy
Superintendent’s name(s): Pat Sullivan, Troy Clinger
What percentage of the work scope was self-performed by your company? : 75%
As the Hudsonville area grew, so did the need to expand their schools. Hudsonville Public Schools broke ground on a new 112,000 SF fifth and sixth grade campus and Burgess Concrete was able to provide them with 40,000 SF of timeless poured and polished concrete floors.
Facts
Submitter: Burgess Concrete Construction
Architect: GMB Architecture & Engineering
Size: 40,000 SF
Title: Hudsonville Public Schools – 5/6 Building
Location: Hudsonville, MI
Date contract completed: August 2023
Final contract value: $508,000
Project manager’s name: Al Jeurink
Superintendent’s name(s): Jordan Burgess, Gale Baartman, Kirt Smith
What percentage of the work scope was self-performed by your company? : 94%
This project consisted of five buildings, totaling 170,000 SF. Each building had its own schedule with overlap. Most of the eight-inch floors sloped to drains and were placed on insulation for in-floor heat. Building flatwork, foundations and excavations of footings was the entire scope.
Facts
Submitter: Van Laan Concrete Construction
Size: 170,000 SF
Title: Road Commission of Kalamazoo County – Phase II
Location: Kalamazoo, Michigan
Date contract completed: February 2024
Final contract value: $3,825,000
Project manager’s name: Josh Van Laan
Superintendent’s name(s): Ben Hildebrand
What percentage of the work scope was self-performed by your company? 95%