West Michigan Beef Company – Processing Facility

Story

The entire project covered 90,000 SF, it began in the fall and continued through the winter months. Besides, most of the walls were tall, radiused, and had multiple elevations, difficult to form. The freezer floors were placed on insulation and had hardener broadcast into the surface. The team was challenged by ten different USDA curb wall section details, totaling over half a mile in length.

Facts

Submitter: Van Laan Concrete Construction

Size: 90,000 SF

Title: West Michigan Beef Company – Processing Facility

Location: Hudsonville, MI

Date contract completed: January 2024

Final contract value: $1,600,000

Project manager’s name: Josh Van Laan

Superintendent’s name(s): Keegan Forman, Terry Jordan

What percentage of the work scope was self-performed by your company?: 100%

Shanty Creek Resort – Lodge Entrance

Story

Kent Companies masterfully designed and built the lodge entrance at Shanty Creek. Work consisted of walls to frame the building, steps and caps, core drilled railings, and integral coloring and stamping to complement the natural lumber.

Facts

Submitter: Kent Companies

Architect: Performance Engineers

Size: 18,000 SF

Title: Shanty Creek Resort – Lodge Entrance

Location: Bellaire, Michigan

Date contract completed: September 2023

Final contract value: $218,000

Project manager’s name: Jason Harrall

Superintendent’s name(s): Tony Kenner, Clayton Schlotterbeck

What percentage of the work scope was self-performed by your company? : 100%

WINNER: Studio Park Tower

Story

Kent Companies built this 17-story multifamily structure on a zero lot line site with the use of the Doka Safety Wall system. Studio Park Tower is the fifth-tallest building in the city and built atop an existing six-level parking structure.

Facts

Submitter: Kent Companies

Architect: Integrated Architecture

Size: 224,000 SF

Title: Studio Park Tower

Location: Grand Rapids, Michigan

Date contract completed: April 2024

Final contract value: $10,400,000

Project manager’s name: Steve McCoy

Superintendent’s name(s): Pat Sullivan, Troy Clinger

What percentage of the work scope was self-performed by your company? : 75%

Hudsonville Public Schools – 5/6 Building

Story

As the Hudsonville area grew, so did the need to expand their schools. Hudsonville Public Schools broke ground on a new 112,000 SF fifth and sixth grade campus and Burgess Concrete was able to provide them with 40,000 SF of timeless poured and polished concrete floors.

Facts

Submitter: Burgess Concrete Construction

Architect: GMB Architecture & Engineering

Size: 40,000 SF

Title: Hudsonville Public Schools – 5/6 Building

Location: Hudsonville, MI

Date contract completed: August 2023

Final contract value: $508,000

Project manager’s name: Al Jeurink

Superintendent’s name(s): Jordan Burgess, Gale Baartman, Kirt Smith

What percentage of the work scope was self-performed by your company? : 94%

Road Commission of Kalamazoo County – Phase II

Story

This project consisted of five buildings, totaling 170,000 SF. Each building had its own schedule with overlap. Most of the eight-inch floors sloped to drains and were placed on insulation for in-floor heat. Building flatwork, foundations and excavations of footings was the entire scope. 

Facts

Submitter: Van Laan Concrete Construction

Size: 170,000 SF

Title: Road Commission of Kalamazoo County – Phase II

Location: Kalamazoo, Michigan

Date contract completed: February 2024

Final contract value: $3,825,000

Project manager’s name: Josh Van Laan

Superintendent’s name(s): Ben Hildebrand

What percentage of the work scope was self-performed by your company? 95%