Located within the restricted AOA of Gerald R. Ford International Airport, this project required careful coordination, especially for concrete and asphalt work. Close proximity to the runway and collaboration with the FAA and Air Traffic Control added complexity. Despite challenges, the project was completed on time and on budget.
Facts
Submitter: FCC Construction Inc.
Architect: DLZ
Title: Gerald R. Ford International Airport — Snow Removal Equipment Building
Size: 60,000 SF
Location: Kentwood, MI
Date contract completed: October 2024
Final contract value: $7,350,000
Project manager’s name: James Zehr
Superintendent’s name(s): Nick Dent
What percentage of the work scope was self-performed by your company? 30%
This 16,500 SF, indoor/outdoor pickleball facility brings a state-of-the-art sports and recreation space to the local community. Featuring indoor/outdoor courts, heated sidewalks, turf areas, and acoustical fencing, the project delivered year-round recreation with minimal disruption to operations and thoughtful integration into the surrounding community.
Facts
Submitter: Lakewood Construction
Architect: AMDG Architects, Lakewood Architecture
Size: 16,500 SF
Location: Grand Rapids, MI
Date contract completed: July 2024
Final contract value: $3,250,000
Project manager’s name: Chad Nienhuis
Superintendent’s name(s): Zac Smith
What percentage of the work scope was self-performed by your company? 36%
Fox Ford’s new pre-engineered metal building is designed to support top-tier vehicle service with the space, style, and efficiency that today’s operations demand. The use of wide bay joists, insulated metal panels, and the mezzanine creates a functional building that looks good.
Facts
Submitter: Pioneer Construction Inc
Architect: Paradigm Design
Size: 50,000 SF
Location: Grand Rapids, MI
Date contract completed: February 2025
Final contract value: $2,100,000
Project manager’s name: Adam Wheeler
Superintendent’s name(s): Steve Suchowian
What percentage of the work scope was self-performed by your company? 100%
Impact Dynamic Training’s mission is “to provide mindful teaching and coaching to each individual athlete while enhancing their skills and building relationships in the process.” This new facility serves as the company’s headquarters and provides an inviting environment where volleyball and pickleball communities can gather for support, encouragement, and fun.
Facts
Submitter: Veneklasen Construction
Architect: Andrus Architecture
Size: 36,000 SF
Title: Impact Dynamic Training
Location: Hudsonville, MI
Date contract completed: March 2023
Final contract value: $3,432,000
Project manager’s name: Cody Klomes
Superintendent’s name(s): Kasey Chubb
What percentage of the work scope was self-performed by your company? 35%
This project consisted of a new vehicle maintenance building, an addition to existing hangar, and a new main hangar featuring a 230 FT clearspan and additional space for office and storage.
Facts
Submitter: Pioneer Construction
Architect: Tectonic Management Group
Size: 74,000 SF
Title: Duncan Aviation
Location: Battle Creek, MI
Date contract completed: February 2024
Final contract value: $11,326,000
Project manager’s name: Adam Wheeler
Superintendent’s name(s): Drake Walker, Steve Suchowian, Danny Clayton
What percentage of the work scope was self-performed by your company? 100%
The New Holland Brewing Battle Creek location includes an inviting outdoor beer garden that seamlessly integrates with the existing brick structure of the main building. Situated in the heart of Battle Creek, coordinating deliveries and staging materials posed logistical challenges due to the limited space. The team had to use an off-site laydown area as they couldn’t stage much within the building footprint. The building itself showcases beautiful architectural finishes, including a standing seam roof and a ceiling liner panel.
Facts
Submitter: Pioneer Construction
Architect: J. Andrew Baer Architect
Size: 4,000 SF
Title: New Holland Brewing – Battle Creek Brewpub
Location: Battle Creek, MI
Date contract completed: January 2023
Final contract value: $3,165,000
Project manager’s name: Adam Wheeler
Superintendent’s name(s): Drake Walker
What percentage of the work scope was self-performed by your company? 100%